Project intelligenceTDLR TABS2025012943Additions to Existing Building
Funding type

This project involves public funds, public land, or is a Federally funded roadway project.

Greenwood High School CTE and Additionals & Renovations Phase 1

2700 FM 1379, Midland, TX, 79706

Opening ~Oct 2026Review Complete

Greenwood High School CTE and Additionals & Renovations Phase 1 is a additions to existing building project at 2700 FM 1379, Midland, in Midland County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Under construction, estimated completion Oct 2026. The project has an estimated value of $15.8M across about 34,500 sq ft.

Estimated project value
$15.8M
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
34,500 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$458/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
1y 6mo
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Feb 27, 2025584 days across supplied datesOct 4, 2026

4 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Review complete · TDLR filing

    The filing records completion of the accessibility review.

    Same day as the preceding date shown.

    Source: TDLR filing

    View source record
  3. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    34 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    550 days after the preceding date shown.

    Source: TDLR filing

    View source record

Review Complete

Design review complete, construction may proceed

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 79706 (Midland)

One email per change. Unsubscribe in one click. Privacy.

Greenwood High School CTE and Additionals & Renovations Phase 1 is a Additions to Existing Building project located at 2700 FM 1379 in Midland, Texas. The project has an estimated value of $15.8M covering 34,500 sq ft. Greenwood ISD is the property owner and Parkhill(Austin Moore)cg is the design firm of record. The project was registered with TDLR on February 27, 2025.

Frequently Asked Questions

What is Greenwood High School CTE and Additionals & Renovations Phase 1?

Greenwood High School CTE and Additionals & Renovations Phase 1 is a additions to existing building project at 2700 FM 1379 in Midland, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Project consists of a 30,000 s.f addition for CTE spaces and interior renovation of approximately 4,500 s.f. for Lifeskills area.

Is Greenwood High School CTE and Additionals & Renovations Phase 1 open in Midland?

Greenwood High School CTE and Additionals & Renovations Phase 1 is still under construction in Midland, TX, with an estimated completion of Oct 2026 according to its TDLR registration.

Where is Greenwood High School CTE and Additionals & Renovations Phase 1 located?

Greenwood High School CTE and Additionals & Renovations Phase 1 is located at 2700 FM 1379, Midland, TX, 79706, in Midland County.

Who is the owner or developer of Greenwood High School CTE and Additionals & Renovations Phase 1?

Greenwood ISD is the property owner/developer of record for Greenwood High School CTE and Additionals & Renovations Phase 1, per its TDLR project registration.

Who is the architect or design firm for Greenwood High School CTE and Additionals & Renovations Phase 1?

Parkhill(Austin Moore)cg is the design firm of record for Greenwood High School CTE and Additionals & Renovations Phase 1, according to its TDLR filing.

How much does Greenwood High School CTE and Additionals & Renovations Phase 1 cost and how big is it?

Greenwood High School CTE and Additionals & Renovations Phase 1 has an estimated construction value of $15.8M and approximately 34,500 square feet (about $458/sqft), based on its TDLR filing.

Scope of Work

Project consists of a 30,000 s.f addition for CTE spaces and interior renovation of approximately 4,500 s.f. for Lifeskills area.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

2700 FM 1379, Midland, TX, 79706

32.02767, -101.89575

Watch all construction in 79706 (Midland)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.