โœ…Inspection Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

S. Carpenter St (CSJ: 0909-22-214)

From: SH 164 To: Bowie St & Lumkin St, Mart, TX 76664, Mart, TX, 76664
Final Inspection85%

๐Ÿ“ŠProject Metrics

TDLR #TABS2025018583
$1.0M
Project Value
26,577
Square Feet
$38/sqft
Cost/SqFt
5 months
Duration
Registered:May 8, 2025
Start:Nov 3, 2025
Target:Mar 31, 2026
Remaining:37 days
โœ…

Inspection Complete

Final inspection completed, awaiting project closure

๐Ÿ“‹Scope of Work

Construct pedestrian infrastructure consisting of sidewalks, crosswalks, ADA ramps and signing.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
May 8, 2025
Review Complete
+267d
May 8, 2025
Inspection Complete
January 30, 2026
Construction Start
November 3, 2025
Expected Completion
March 31, 2026