๐Ÿ“Review Complete๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Midland Freshman High Renovations

101 E. Gist Ave., Midland, TX, 79705
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2025020822
$28.7M
Project Value
60,392
Square Feet
$475/sqft
Cost/SqFt
1y 11mo
Duration
Registered:Jun 9, 2025
Start:Aug 4, 2025
Target:Jun 30, 2027
Remaining:493 days
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Additions and alterations

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
June 9, 2025
Review Complete
June 9, 2025
Construction Start
August 4, 2025
Expected Completion
June 30, 2027

๐Ÿ“Location & Views

Open in MapsGet Directions|31.98001, -102.07078