HARP3 DFW - Gate D36 Restroom Renovations in Dfw Airport, TX
2024 S. International Parkway DFW Airport, Dfw Airport, TX, 75261
HARP3 DFW - Gate D36 Restroom Renovations is a renovation/alteration project at 2024 S. International Parkway DFW Airport, Dfw Airport, in Tarrant County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Construction complete (TDLR inspection passed Aug 2026). The project has an estimated value of $4.0M across about 4,500 sq ft.
- Estimated project value
- $4.0M
About this figure
Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.
- Reported floor area
- 4,500 ft²
About this figure
Square footage reported for this scope of work. It may cover only part of a larger property.
- Estimated cost / ft²
- $889/sqft
About this figure
Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.
- Scheduled duration
- 4 months
About this figure
The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.
The project record
Project timeline
Explore filed milestones and scheduled dates. Open a milestone for its source.
5 timeline dates shown.
Project registered · TDLR filing
Registration of the project with the Texas Department of Licensing and Regulation.
Source: TDLR filing
View source recordScheduled construction start · Scheduled date
A date supplied in the filing; this does not confirm that work started or finished.
73 days after the preceding date shown.
Source: TDLR filing
View source recordReview complete · TDLR filing
The filing records completion of the accessibility review.
41 days after the preceding date shown.
Source: TDLR filing
View source recordScheduled completion · Scheduled date
A date supplied in the filing; this does not confirm that work started or finished.
80 days after the preceding date shown.
Source: TDLR filing
View source recordInspection complete · TDLR filing
The filing records completion of the accessibility inspection.
158 days after the preceding date shown.
Source: TDLR filing
View source record
📰About HARP3 DFW - Gate D36 Restroom Renovations
Terminal D at DFW Airport has completed its renovation of public restrooms and upgrades. The project, filed as HARP3 DFW - Gate D36 Restroom Renovations, covers 4,500 square feet of facility space. Construction is finished, with the building passing its final TDLR accessibility inspection in August 2026.
The work took place at 2024 S. International Parkway in Dfw Airport, Tarrant County. DFW Airport is the owner of record. Cannon Design, Inc. served as the design firm. Christopher R Hinkle is the registered accessibility specialist associated with the filing. The estimated cost for this renovation and alteration was $4,000,000.
Project Scope and Scale
The scope of work included restroom renovations and upgrades within Terminal D. At 4,500 square feet, the project size is comparable to the median renovation size in Tarrant County, which is 3,900 square feet. However, the cost per square foot is $889. This figure is above the county median of $79 per square foot for similar renovation and alteration filings.
The scheduled build window for this project was 121 days. This duration is longer than the county median scheduled build window of 92 days. The estimated total cost of $4,000,000 places the project in the top quarter of estimated costs for renovation and alteration projects in the county, where the median is $250,000.
Regulatory Timeline
The project was registered with TDLR in August 2025. Plan review was completed in December 2025. Construction began in October 2025. The filing indicated a completion date of March 2026. The final inspection was passed in August 2026, confirming the TDLR status as Inspection Complete. This project involves public funds, public land, or is a Federally funded roadway project.
DFW Airport has six other TDLR-registered projects totaling $113,630,000. These include Terminal E Satellite and DFW Terminal C. Cannon Design, Inc. has four other TDLR-registered projects totaling $13,550,000, including work on Terminal A and Terminal E at DFW Airport. Nearby registered projects include DFW Terminal D and E, Terminal B, and Terminal A DFW Airport.
Inspection Complete
Final inspection completed, awaiting project closure
Follow this project
Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.
Or watch all projects in 75261 (Dfw Airport)
One email per change. Unsubscribe in one click. Privacy.
HARP3 DFW - Gate D36 Restroom Renovations is a Renovation/Alteration project located at 2024 S. International Parkway DFW Airport, Dfw Airport, TX 75261 in Dfw Airport, Texas. The project has an estimated value of $4.0M covering 4,500 sq ft. DFW Airport is the property owner and Cannon Design, Inc. is the design firm of record. The project was registered with TDLR on August 19, 2025.
Frequently Asked Questions
Is the Terminal D restroom renovation complete?
Yes, construction is complete. The project passed its final TDLR accessibility inspection in August 2026.
Who designed the Terminal D restroom upgrades?
Cannon Design, Inc. is the design firm of record for this project.
What is the address of this project?
The project is located at 2024 S. International Parkway, DFW Airport, TX 75261.
Who is the owner of record?
DFW Airport is the owner and developer of record for this project.
What is HARP3 DFW - Gate D36 Restroom Renovations?
HARP3 DFW - Gate D36 Restroom Renovations is a renovation/alteration project at 2024 S. International Parkway DFW Airport in Dfw Airport, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Terminal D public restroom renovations and upgrades - 4,500 SF
Is HARP3 DFW - Gate D36 Restroom Renovations open in Dfw Airport?
Construction on HARP3 DFW - Gate D36 Restroom Renovations is complete — TDLR records show the project passed its required accessibility inspection in Aug 2026. The building is finished and very likely open.
Where is HARP3 DFW - Gate D36 Restroom Renovations located?
HARP3 DFW - Gate D36 Restroom Renovations is located at 2024 S. International Parkway DFW Airport, Dfw Airport, TX, 75261, in Tarrant County.
Who is the owner or developer of HARP3 DFW - Gate D36 Restroom Renovations?
DFW Airport is the property owner/developer of record for HARP3 DFW - Gate D36 Restroom Renovations, per its TDLR project registration.
Who is the architect or design firm for HARP3 DFW - Gate D36 Restroom Renovations?
Cannon Design, Inc. is the design firm of record for HARP3 DFW - Gate D36 Restroom Renovations, according to its TDLR filing.
How much does HARP3 DFW - Gate D36 Restroom Renovations cost and how big is it?
HARP3 DFW - Gate D36 Restroom Renovations has an estimated construction value of $4.0M and approximately 4,500 square feet (about $889/sqft), based on its TDLR filing.
Scope of Work
Terminal D public restroom renovations and upgrades - 4,500 SF
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
Location & views
2024 S. International Parkway DFW Airport, Dfw Airport, TX, 75261
Explore the supplied address
A precise map point has not been loaded. Choose to look up the address, or open it in Google Maps using the link below.
Related Projects
Same Owner
$111.7M totalWatch all construction in 75261 (Dfw Airport)
A short email when anything new is filed in this ZIP. One ZIP free, weekly.
Unsubscribe in one click. Privacy.
Keep exploring
What else is changing in Dfw Airport?
See the surrounding filings, compare the reported schedules, and follow the places that matter to you.