Project intelligenceTDLR TABS2026008777Renovation/Alteration
Funding type

This project involves public funds, public land, or is a Federally funded roadway project.

2026 P2B Security Vestibule Upgrades - Meridiana Elementry School in Rosharon, TX

9815 Meridiana Parkway, Rosharon, TX, 77496

Construction complete · Sep 2026Inspection Complete

2026 P2B Security Vestibule Upgrades - Meridiana Elementry School is a renovation/alteration project at 9815 Meridiana Parkway, Rosharon, in Brazoria County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Construction complete (TDLR inspection passed Sep 2026). The project has an estimated value of $350K across about 1,400 sq ft.

Estimated project value
$350K
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
1,400 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$250/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
2 months
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Dec 22, 2025260 days across supplied datesSep 8, 2026

5 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Review complete · TDLR filing

    The filing records completion of the accessibility review.

    22 days after the preceding date shown.

    Source: TDLR filing

    View source record
  3. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    132 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    71 days after the preceding date shown.

    Source: TDLR filing

    View source record
  5. Inspection complete · TDLR filing

    The filing records completion of the accessibility inspection.

    35 days after the preceding date shown.

    Source: TDLR filing

    View source record

📰About 2026 P2B Security Vestibule Upgrades - Meridiana Elementry School

The renovation of the main entry security vestibule at Meridiana Elementary School in Rosharon is complete. The project, filed under the name 2026 P2B Security Vestibule Upgrades - Meridiana Elementry School, involved upgrading approximately 1,400 sq ft of existing educational space. The work was registered with TDLR in December 2025 and passed its final TDLR accessibility inspection in September 2026. This confirms that the construction phase is finished and the facility has met state accessibility standards.

Alvin Independent School District owns the project, which was designed by JMB2 Architecture, Inc. The estimated cost for this specific renovation was $350,000. This figure places the project above the median estimated cost of $250,000 for renovation and alteration filings in Brazoria County. The cost per square foot is $250, which is higher than the county median of $90 per square foot for similar projects.

The scheduled build window for this project was 71 days, from May 2026 to August 2026. This timeline is shorter than the median scheduled build window of 95 days for comparable projects in the county. The scope of work focused specifically on the main entry security vestibule, ensuring that the new infrastructure integrates with the remaining existing educational facility. The project utilized public funds and is located on public land within Brazoria County.

Meridiana Elementary School is one of several similar projects managed by Alvin Independent School District. The district has six other TDLR-registered projects totaling $55,550,000, including Alvin High School and multiple other elementary schools in Alvin, Manvel, Pearland, and Rosharon. Most of these comparable elementary school projects have also reached inspection complete status. JMB2 Architecture, Inc. has similarly completed five other projects for the district, indicating a consistent pattern of infrastructure upgrades across the school system.

The site is located at 9815 Meridiana Parkway in Rosharon, TX 77496. Nearby businesses include Iowa Colony City Park at Meridiana and Meridiana by Rise Communities. The project’s completion adds to the district’s ongoing efforts to modernize school infrastructure. The specific focus on security vestibules reflects a broader trend in educational facilities to enhance safety and accessibility at primary entry points. The final status of the project is Inspection Complete, confirming that all required work has been verified by state authorities.

Project Details and Context

The renovation was part of a larger initiative by Alvin Independent School District to upgrade security and accessibility features in its elementary schools. The use of public funds and the involvement of a registered accessibility specialist, Kam-hung Kenneth Woo, ensure compliance with state regulations. The project’s completion in September 2026 marks the end of the construction period, which began in May 2026. The total investment of $350,000 for 1,400 sq ft of work aligns with the district’s strategy of targeted, high-impact improvements to existing facilities.

Inspection Complete

Final inspection completed, awaiting project closure

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 77496 (Rosharon)

One email per change. Unsubscribe in one click. Privacy.

2026 P2B Security Vestibule Upgrades - Meridiana Elementry School is a Renovation/Alteration project located at 9815 Meridiana Parkway, Rosharon, TX 77496 in Rosharon, Texas. The project has an estimated value of $350K covering 1,400 sq ft. Alvin Independent School District is the property owner and JMB2 Architecture, Inc. is the design firm of record. The project was registered with TDLR on December 22, 2025.

Frequently Asked Questions

Is Meridiana Elementary School open?

The TDLR record confirms the construction is complete and the final TDLR accessibility inspection passed in September 2026. The record does not specify business hours or public opening status.

Who built the security vestibule?

Alvin Independent School District is the owner of record. JMB2 Architecture, Inc. is the design firm. The project was registered with TDLR and passed its final inspection in September 2026.

How much did the renovation cost?

The estimated cost for the 1,400 sq ft security vestibule renovation was $350,000. This is above the Brazoria County median cost of $250,000 for similar renovation projects.

When was the project completed?

Construction started in May 2026 and the scheduled completion date was August 2026. The final TDLR accessibility inspection was passed in September 2026, marking the project as complete.

What other projects has this school district done?

Alvin Independent School District has six other TDLR-registered projects totaling $55,550,000. These include Alvin High School and several other elementary schools in the region, most of which are inspection complete.

What is 2026 P2B Security Vestibule Upgrades - Meridiana Elementry School?

2026 P2B Security Vestibule Upgrades - Meridiana Elementry School is a renovation/alteration project at 9815 Meridiana Parkway in Rosharon, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Main Entry Security Vestibule Renovation Upgrades (approximately 1,400sf per renovation area per school) to Existing Educational Facility to remain.

Is 2026 P2B Security Vestibule Upgrades - Meridiana Elementry School open in Rosharon?

Construction on 2026 P2B Security Vestibule Upgrades - Meridiana Elementry School is complete — TDLR records show the project passed its required accessibility inspection in Sep 2026. The building is finished and very likely open.

Where is 2026 P2B Security Vestibule Upgrades - Meridiana Elementry School located?

2026 P2B Security Vestibule Upgrades - Meridiana Elementry School is located at 9815 Meridiana Parkway, Rosharon, TX, 77496, in Brazoria County.

Who is the owner or developer of 2026 P2B Security Vestibule Upgrades - Meridiana Elementry School?

Alvin Independent School District is the property owner/developer of record for 2026 P2B Security Vestibule Upgrades - Meridiana Elementry School, per its TDLR project registration.

Who is the architect or design firm for 2026 P2B Security Vestibule Upgrades - Meridiana Elementry School?

JMB2 Architecture, Inc. is the design firm of record for 2026 P2B Security Vestibule Upgrades - Meridiana Elementry School, according to its TDLR filing.

How much does 2026 P2B Security Vestibule Upgrades - Meridiana Elementry School cost and how big is it?

2026 P2B Security Vestibule Upgrades - Meridiana Elementry School has an estimated construction value of $350K and approximately 1,400 square feet (about $250/sqft), based on its TDLR filing.

Scope of Work

Main Entry Security Vestibule Renovation Upgrades (approximately 1,400sf per renovation area per school) to Existing Educational Facility to remain.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

9815 Meridiana Parkway, Rosharon, TX, 77496

Explore the supplied address

A precise map point has not been loaded. Choose to look up the address, or open it in Google Maps using the link below.

Location by street address

Watch all construction in 77496 (Rosharon)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.

Keep exploring

What else is changing in Rosharon?

See the surrounding filings, compare the reported schedules, and follow the places that matter to you.