๐Project Registered๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Kingsville Sidewalk Project (CSJ: 0916-02-025)
Along W. Johnston Ave and S. Armstrong St, Kingsville, TX 78363, Kingsville, TX, 78363
Pre-Construction15%
๐Project Metrics
TDLR #TABS2026013521$1.3M
Project Value
58,000
Square Feet
$23/sqft
Cost/SqFt
7 months
Duration
Registered:Feb 25, 2026
Start:Apr 29, 2026
Target:Dec 1, 2026
Remaining:277 days
๐
Project Registered
Project has been registered with TDLR and is in pre-construction phase
๐Scope of Work
Construction of sidewalk, ADA ramps and pedestrian elements. Drainage, landscaping and traffic elements.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
February 25, 2026
Construction Start
April 29, 2026
Expected Completion
December 1, 2026
๐Related Projects
๐คSame Owner
$10.2M total๐๏ธSame Design Firm
$79.0M totalProperty Owner
๐ค
City of Kingsville
4 projects ยท $10.2M
View all projects
400 W. King Ave., Kingsville, Texas 78363
Design Firm
๐๏ธ
LJA Engineering, Inc.
4 projects ยท $79.0M
View all projects
6060 North Central Expressway, Suite 400, Dallas, Texas 75206