Keller Sidewalk Additions-Keller Middle School

City of Keller Public Right of Way, Keller, TX, 76248

Construction complete · Oct 2026Inspection Complete

Keller Sidewalk Additions-Keller Middle School is a new construction project at City of Keller Public Right of Way, Keller, in Tarrant County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Construction complete (TDLR inspection passed Oct 2026). The project has an estimated value of $250K across about 10,000 sq ft.

Estimated project value
$250K
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
10,000 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$25/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
5 months
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

May 14, 2026230 days across supplied datesDec 30, 2026

5 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Review complete · TDLR filing

    The filing records completion of the accessibility review.

    39 days after the preceding date shown.

    Source: TDLR filing

    View source record
  3. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    38 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Inspection complete · TDLR filing

    The filing records completion of the accessibility inspection.

    79 days after the preceding date shown.

    Source: TDLR filing

    View source record
  5. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    74 days after the preceding date shown.

    Source: TDLR filing

    View source record

📰About Keller Sidewalk Additions-Keller Middle School

The project known as Keller Sidewalk Additions-Keller Middle School is complete. Construction finished with a final TDLR accessibility inspection passed in October 2026. The work involved the installation of 10,000 square feet of new sidewalks along Charles St, Lorine St, Ruby St, Pearl St, Elm St, and Minnie St. These additions connect new walkways to existing infrastructure within the City of Keller Public Right of Way.

The City of Keller served as the owner of record for this new construction project. The estimated cost was $250,000, which calculates to $25 per square foot. This figure is below the Tarrant County median of $120 per square foot for similar new construction filings. The scheduled build window was 153 days, shorter than the county median of 214 days. The project was registered with the Texas Department of Licensing and Regulation in May 2026.

Design and Regulatory Oversight

Neel-Schaffer, Inc. was the design firm of record for the project. George A Patterson served as the registered accessibility specialist. Plan review was completed in June 2026, and construction began in July 2026. The filing indicated that the project involved public funds and public land. The TDLR status is recorded as Inspection Complete, confirming that the accessibility requirements were met during the final phase.

This project is one of several infrastructure investments by the City of Keller. The city has six other TDLR-registered projects totaling $2,289,000, including various sidewalk and facility improvements. Neel-Schaffer, Inc. has also designed two other projects for the city, with a combined value of $572,000. The local context for this work is the Keller area, which has a population of about 40,130 and a median household income of $161,383 according to Census estimates for ZIP code 76248.

The completion of these sidewalks improves pedestrian connectivity in the Tarrant County community. The project scope was specifically defined to link new sections to existing paths, ensuring a continuous network for residents and students. The registration and inspection process followed standard state protocols for public works. The final TDLR accessibility inspection in October 2026 marked the end of the construction and review cycle for this specific filing.

Inspection Complete

Final inspection completed, awaiting project closure

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 76248 (Keller)

One email per change. Unsubscribe in one click. Privacy.

Keller Sidewalk Additions-Keller Middle School is a New Construction project located at City of Keller Public Right of Way, Keller, TX 76248 in Keller, Texas. The project has an estimated value of $250K covering 10,000 sq ft. City of Keller is the property owner and Neel-Schaffer ,Inc. is the design firm of record. The project was registered with TDLR on May 14, 2026.

Frequently Asked Questions

Is the Keller Sidewalk Additions project finished?

Yes, the project is complete. The final TDLR accessibility inspection was passed in October 2026, and the TDLR status is recorded as Inspection Complete.

Who designed the new sidewalks?

Neel-Schaffer, Inc. was the design firm of record. George A Patterson served as the registered accessibility specialist for the project.

What is the total size of the new sidewalks?

The project involved the installation of 10,000 square feet of new sidewalks along six streets in the City of Keller.

How much did the project cost?

The estimated cost was $250,000. This equates to $25 per square foot, which is below the Tarrant County median for similar new construction filings.

Which streets received the new sidewalks?

New sidewalks were installed along Charles St, Lorine St, Ruby St, Pearl St, Elm St, and Minnie St to connect to existing walkways.

What is Keller Sidewalk Additions-Keller Middle School?

Keller Sidewalk Additions-Keller Middle School is a new construction project at City of Keller Public Right of Way in Keller, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Installation of new sidewalks along Charles St, Lorine St, Ruby St, Pearl St, Elm St, and Minnie St to connect new sidewalks to existing sidewalks. Estimated at 10000 SF of new sidewalks.

Is Keller Sidewalk Additions-Keller Middle School open in Keller?

Construction on Keller Sidewalk Additions-Keller Middle School is complete — TDLR records show the project passed its required accessibility inspection in Oct 2026. The building is finished and very likely open.

Where is Keller Sidewalk Additions-Keller Middle School located?

Keller Sidewalk Additions-Keller Middle School is located at City of Keller Public Right of Way, Keller, TX, 76248, in Tarrant County.

Who is the owner or developer of Keller Sidewalk Additions-Keller Middle School?

City of Keller is the property owner/developer of record for Keller Sidewalk Additions-Keller Middle School, per its TDLR project registration.

Who is the architect or design firm for Keller Sidewalk Additions-Keller Middle School?

Neel-Schaffer ,Inc. is the design firm of record for Keller Sidewalk Additions-Keller Middle School, according to its TDLR filing.

How much does Keller Sidewalk Additions-Keller Middle School cost and how big is it?

Keller Sidewalk Additions-Keller Middle School has an estimated construction value of $250K and approximately 10,000 square feet (about $25/sqft), based on its TDLR filing.

Scope of Work

Installation of new sidewalks along Charles St, Lorine St, Ruby St, Pearl St, Elm St, and Minnie St to connect new sidewalks to existing sidewalks. Estimated at 10000 SF of new sidewalks.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

City of Keller Public Right of Way, Keller, TX, 76248

Explore the supplied address

A precise map point has not been loaded. Choose to look up the address, or open it in Google Maps using the link below.

Location by street address

Watch all construction in 76248 (Keller)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.