Project intelligenceTDLR TABS2026021254New Construction
Funding type

This project is privately funded, on private land for private use.

Take 5 Oil Change

Hwy 105 & Buffalo Springs Dr, Montgomery, TX, 77356

Opening ~Oct 2026Review Complete

Take 5 Oil Change is a new construction project at Hwy 105 & Buffalo Springs Dr, Montgomery, in Montgomery County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Under construction, estimated completion Oct 2026. The project has an estimated value of $500K across about 2,130 sq ft.

Estimated project value
$500K
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
2,130 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$235/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
4 months
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

Explore the linked construction record and source history

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

May 27, 2026157 days across supplied datesOct 31, 2026

4 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    35 days after the preceding date shown.

    Source: TDLR filing

    View source record
  3. Review complete · TDLR filing

    The filing records completion of the accessibility review.

    36 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    86 days after the preceding date shown.

    Source: TDLR filing

    View source record

📰About Take 5 Oil Change

Take 5 Oil Change is building a new 2,130 sq ft facility at the intersection of Hwy 105 and Buffalo Springs Dr in Montgomery, Texas. The project, filed with the TDLR under the name Take 5 Oil Change - Montgomery, is a new construction effort with an estimated cost of $500,000. Construction began in July 2026 and is scheduled to finish in October 2026.

The development is owned by Take 5 Properties SPV, LLC, which has registered six other TDLR projects across Texas. These include locations in Harker Heights, Port Arthur, Rowlett, Tyler, and Denton, with a combined value of $3,050,000. The design for this Montgomery facility is handled by Altar Group, a firm that has also designed five other Take 5 projects in Houston, Cleveland, Ennis, Willis, and Harker Heights.

The project’s estimated cost of $500,000 is below the median estimated cost of $800,000 for new construction filings in Montgomery County. However, the cost per square foot is $235, which is above the county median of $100 per square foot. The scheduled build window of 122 days is shorter than the county median of 213 days for similar projects.

TDLR completed plan review for this project in August 2026. The status is listed as Review Complete. The registered accessibility specialist for the project is Kari Thomas. The facility is privately funded and located on private land for private use.

Montgomery County’s unemployment rate was 4.8 percent in July 2026, according to FRED data. The ZIP code 77356 has a population of about 31,069 and a median household income of $113,750, based on U.S. Census ACS 2023 five-year estimates. The area is predominantly owner-occupied, with a median home value of $369,200.

Review Complete

Design review complete, construction may proceed

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 77356 (Montgomery)

One email per change. Unsubscribe in one click. Privacy.

Take 5 Oil Change is a New Construction project located at Hwy 105 & Buffalo Springs Dr, Montgomery, TX 77356 in Montgomery, Texas. The project has an estimated value of $500K covering 2,130 sq ft. Take 5 Properties SPV, LLC is the property owner and Altar Group is the design firm of record. The project was registered with TDLR on May 27, 2026.

Frequently Asked Questions

Where is the new Take 5 Oil Change facility located?

The new facility is located at the intersection of Hwy 105 and Buffalo Springs Dr in Montgomery, Texas, within ZIP code 77356.

Who owns and designs the Montgomery project?

Take 5 Properties SPV, LLC is the owner of record, and Altar Group is the design firm of record for this new construction project.

What is the estimated cost and size?

The project has an estimated cost of $500,000 and a total area of 2,130 square feet, resulting in a cost of $235 per square foot.

Is the construction finished?

No, construction started in July 2026 and is scheduled to finish in October 2026. TDLR plan review was completed in August 2026.

Is the business open for service?

The TDLR record tracks construction status, not business operations. The project is scheduled to finish in October 2026, but no opening date is provided in the filing.

What is Take 5 Oil Change?

Take 5 Oil Change is a new construction project at Hwy 105 & Buffalo Springs Dr in Montgomery, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: New oil change facility

Is Take 5 Oil Change open in Montgomery?

Take 5 Oil Change is still under construction in Montgomery, TX, with an estimated completion of Oct 2026 according to its TDLR registration.

Where is Take 5 Oil Change located?

Take 5 Oil Change is located at Hwy 105 & Buffalo Springs Dr, Montgomery, TX, 77356, in Montgomery County.

Who is the owner or developer of Take 5 Oil Change?

Take 5 Properties SPV, LLC is the property owner/developer of record for Take 5 Oil Change, per its TDLR project registration.

Who is the architect or design firm for Take 5 Oil Change?

Altar Group is the design firm of record for Take 5 Oil Change, according to its TDLR filing.

How much does Take 5 Oil Change cost and how big is it?

Take 5 Oil Change has an estimated construction value of $500K and approximately 2,130 square feet (about $235/sqft), based on its TDLR filing.

Scope of Work

New oil change facility

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

Hwy 105 & Buffalo Springs Dr, Montgomery, TX, 77356

Location by street address

Watch all construction in 77356 (Montgomery)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.

Keep exploring

What else is changing in Montgomery?

See the surrounding filings, compare the reported schedules, and follow the places that matter to you.