Project intelligenceTDLR EABPRJB5801134New Construction
Funding type

This project involves public funds, public land, or is a Federally funded roadway project.

FM 969 PHASE 1 AND PHASE 2

FM 3177 TO HUNTERS BEND, Austin, TX, 78724

Construction complete · Jul 2020Inspection Complete

FM 969 PHASE 1 AND PHASE 2 is a new construction project at FM 3177 TO HUNTERS BEND, Austin, in Travis County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Construction complete (TDLR inspection passed Jul 2020). The project has an estimated value of $600K.

Estimated project value
$600K
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
Not supplied
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
6y 7mo
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Jan 1, 20142,380 days across supplied datesJul 8, 2020

4 timeline dates shown.

  1. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    Source: TDLR filing

    View source record
  2. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    260 days after the preceding date shown.

    Source: TDLR filing

    View source record
  3. Inspection complete · TDLR filing

    The filing records completion of the accessibility inspection.

    2,120 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    Same day as the preceding date shown.

    Source: TDLR filing

    View source record

Inspection Complete

Final inspection completed, awaiting project closure

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 78724 (Austin)

One email per change. Unsubscribe in one click. Privacy.

FM 969 PHASE 1 AND PHASE 2 is a New Construction project located at FM 3177 TO HUNTERS BEND, Austin, TX 78724 in Austin, Texas. The project has an estimated value of $600K. TXDOT is the property owner and LJA ENGINEERING INC is the design firm of record. The project was registered with TDLR on September 18, 2014.

Frequently Asked Questions

What is FM 969 PHASE 1 AND PHASE 2?

FM 969 PHASE 1 AND PHASE 2 is a new construction project at FM 3177 TO HUNTERS BEND in Austin, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Widen FM 969 and construct sidewalk along FM 969 from FM3177 to Hunters Bend.

Is FM 969 PHASE 1 AND PHASE 2 open in Austin?

Construction on FM 969 PHASE 1 AND PHASE 2 is complete — TDLR records show the project passed its required accessibility inspection in Jul 2020. The building is finished and very likely open.

Where is FM 969 PHASE 1 AND PHASE 2 located?

FM 969 PHASE 1 AND PHASE 2 is located at FM 3177 TO HUNTERS BEND, Austin, TX, 78724, in Travis County.

Who is the owner or developer of FM 969 PHASE 1 AND PHASE 2?

TXDOT is the property owner/developer of record for FM 969 PHASE 1 AND PHASE 2, per its TDLR project registration.

Who is the architect or design firm for FM 969 PHASE 1 AND PHASE 2?

LJA ENGINEERING INC is the design firm of record for FM 969 PHASE 1 AND PHASE 2, according to its TDLR filing.

How much does FM 969 PHASE 1 AND PHASE 2 cost and how big is it?

FM 969 PHASE 1 AND PHASE 2 has an estimated construction value of $600K, based on its TDLR filing.

Scope of Work

Widen FM 969 and construct sidewalk along FM 969 from FM3177 to Hunters Bend.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

FM 3177 TO HUNTERS BEND, Austin, TX, 78724

30.28786, -97.75614

Related City Permits

Building permits found at or near this location

2301 WINDSOR RD
Same location

Change-out HVAC to existing residence only.

FinalMechanical PermitRemodelAug 2013
View Details
2013-086270 MP
Petrocelli Services Inc.
2305 WINDSOR RD
107 ft away

Install EVSE in garage

FinalElectrical PermitSpecial Inspections ProgramMay 2021
View Details
2021-062668 EP
Grayzer Electric LLC
2215 WINDSOR RD
128 ft away

Replace siding on existing single-family residence. No other changes authorized under this permit.

FinalBuilding PermitRepairApr 2017
$6K
View Details
2017-039727 BP
Home Depot USA Inc
2302 WINDSOR RD
144 ft away

Replace sewer line in the yard replace the sewer line in the yard only.

WithdrawnPlumbing PermitRepairOct 2023
View Details
2023-127986 PP
Service Wizard
2302 WINDSOR RD
144 ft away

Replacement of complete existing central heat and air system with or without duct work

ExpiredMechanical PermitChange OutSep 2019
View Details
2019-181713 MP
All Year Heating & Cooling

Watch all construction in 78724 (Austin)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.