Project intelligenceTDLR EABPRJB8814564New Construction
Funding type

This project is privately funded, on private land for private use.

HONKY TONK KID BBQ in Waco, TX

112 MARY AVE., UNIT 2, Waco, TX, 76701

Target date passed (Jul 2018)Review Complete

HONKY TONK KID BBQ is a new construction project at 112 MARY AVE., UNIT 2, Waco, in McLennan County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Scheduled to finish Jul 2018 per its TDLR filing; no final inspection recorded yet. The project has an estimated value of $70K.

Estimated project value
$70K
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
Not supplied
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
—
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
2 months
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Apr 11, 201881 days across supplied datesJul 1, 2018

4 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Review complete · TDLR filing

    The filing records completion of the accessibility review.

    Same day as the preceding date shown.

    Source: TDLR filing

    View source record
  3. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    20 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    61 days after the preceding date shown.

    Source: TDLR filing

    View source record

Review Complete

Design review complete, construction may proceed

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 76701 (Waco)

One email per change. Unsubscribe in one click. Privacy.

HONKY TONK KID BBQ is a New Construction project located at 112 MARY AVE., UNIT 2, Waco, TX 76701 in Waco, Texas. The project has an estimated value of $70K. BEHRINGER GROUP is the property owner and ABACUS ENGINEERING INC. is the design firm of record. The project was registered with TDLR on April 11, 2018.

Frequently Asked Questions

What is HONKY TONK KID BBQ?

HONKY TONK KID BBQ is a new construction project at 112 MARY AVE., UNIT 2 in Waco, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Shell Building: adding in restrooms, storage areas, cooking area and smoker.

Is HONKY TONK KID BBQ open in Waco?

HONKY TONK KID BBQ was scheduled to finish construction in Jul 2018 according to its TDLR registration, but TDLR has not recorded a final accessibility inspection, so its opening status is not confirmed in the public record.

Where is HONKY TONK KID BBQ located?

HONKY TONK KID BBQ is located at 112 MARY AVE., UNIT 2, Waco, TX, 76701, in McLennan County.

Who is the owner or developer of HONKY TONK KID BBQ?

BEHRINGER GROUP is the property owner/developer of record for HONKY TONK KID BBQ, per its TDLR project registration.

Who is the architect or design firm for HONKY TONK KID BBQ?

ABACUS ENGINEERING INC. is the design firm of record for HONKY TONK KID BBQ, according to its TDLR filing.

How much does HONKY TONK KID BBQ cost and how big is it?

HONKY TONK KID BBQ has an estimated construction value of $70K, based on its TDLR filing.

Scope of Work

Shell Building: adding in restrooms, storage areas, cooking area and smoker.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

112 MARY AVE., UNIT 2, Waco, TX, 76701

Loading location map…
31.55821, -97.12635

Watch all construction in 76701 (Waco)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.