๐ŸProject Closed๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

FY 22 MILL & OVERLAY PHASE 2 (DISTRICT #4)

401 Franklin Avenue, Waco, TX 76701, Waco, TX, 76701
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #TABS2022017608
$3.0M
Project Value
604,260
Square Feet
$5/sqft
Cost/SqFt
9 months
Duration
Registered:Apr 27, 2022
Start:Jul 1, 2022
Target:Apr 1, 2023
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Street mill & overlay, base failure repair, sidewalk and ramps on Windsor Ave, 23rd St, Lasker Ave, Gorman Ave, 13th St & Cumberland Ave.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
April 27, 2022
Project Closed
April 1, 2023
Construction Start
July 1, 2022
Expected Completion
April 1, 2023