๐Ÿ“Review Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project is privately funded, on private land for private use.

KEYSTONE

1424 North Main Street, Pearland, TX 77581, Pearland, TX, 77581
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2022024770
$8.4M
Project Value
49,473
Square Feet
$170/sqft
Cost/SqFt
9 months
Duration
Registered:Jul 27, 2022
Start:Oct 1, 2022
Target:Jun 30, 2023
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

New office/shop facility for Keystone.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
July 27, 2022
Construction Start
October 1, 2022
Expected Completion
June 30, 2023