🏁Project Closed🔧 Renovation/Alteration💵 This project involves public funds, public land, or is a Federally funded roadway project.
2022 Downtown Sidewalks – Anglin Street (Henderson to James)
Anglin Street (Henderson to James), Cleburne, TX 76033, Cleburne, TX, 76033
Completed100%
📊Project Metrics
TDLR #TABS2022025441$365K
Project Value
7,000
Square Feet
$52/sqft
Cost/SqFt
3 months
Duration
Registered:Aug 4, 2022
Start:Sep 26, 2022
Target:Dec 30, 2022
🏁
Project Closed
Project has been completed and closed
📋Scope of Work
Sidewalk removal and replacement (5,974 SY), curb and gutter removal and replacement (576 LF), concrete drive removal and replacement (1,011 SY), plus associated work including adjustment of utilities.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
📅Compliance Timeline
Project Registered
August 4, 2022
Construction Start
September 26, 2022
Expected Completion
December 30, 2022
🔗Related Projects
👤Same Owner
$4.3M total🏛️Same Design Firm
$435K totalProperty Owner
👤
City of Cleburne
Contact: Laura E. Melton
4 projects · $4.3M
View all projects
10 N. Robinson, Cleburne, Texas 76033
Design Firm
🏛️
Childress Engineers
2 projects · $435K
View all projects
211 N. Ridgeway Drive, Cleburne, Texas 76033