Clay Avenue and 4th Street Sidewalk Improvements
City of Waco Right of Way at Clay Avenue, Waco, TX 76706, Waco, TX, 76706
Final Inspection85%
๐Project Metrics
TDLR #TABS2025006649$740K
Project Value
43,560
Square Feet
$17/sqft
Cost/SqFt
8 months
Duration
Registered:Dec 2, 2024
Start:May 1, 2025
Target:Dec 31, 2025
โ
Inspection Complete
Final inspection completed, awaiting project closure
๐Scope of Work
Construction of pedestrian infrastructure along Clay Avenue and 4th street to University Parks Drive
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
December 2, 2024
Review Complete
+446dDecember 2, 2024
Inspection Complete
February 21, 2026
Construction Start
May 1, 2025
Expected Completion
December 31, 2025
๐Related Projects
๐คSame Owner
$10.8M total๐๏ธSame Design Firm
$93.0M totalProperty Owner
๐ค
City of Waco
Contact: Roger Blakley
4 projects ยท $10.8M
View company profile
401 Franklin Avenue, Waco, Texas 76701
Design Firm
๐๏ธ
BGE Inc
4 projects ยท $93.0M
View company profile
3925 Interstate-35, Waco, Texas 76701