๐Review Complete๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Montrose Blvd Reconstruction
Montrose Blvd from Westheimer Rd to W Clay Street, Houston, TX, 77006
Construction50%
๐Project Metrics
TDLR #TABS2025008687$6.3M
Project Value
370,000
Square Feet
$17/sqft
Cost/SqFt
1y 5mo
Duration
Registered:Jan 2, 2025
Start:Jul 20, 2026
Target:Dec 15, 2027
Remaining:654 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Pavement, sidewalks and bus stops replacement
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
January 2, 2025
Review Complete
January 2, 2025
Construction Start
July 20, 2026
Expected Completion
December 15, 2027
๐Related Projects
๐คSame Owner
$2.9M total๐Nearby Projects
Within 1 kmBroadway St (CSJ: 0912-72-846)
At UPRR, Galveston Rd and Harding St, Houston, TX 77012ยท$5.7M
Hockley Meadows Section 3 Landscape Improvements
Intersect. of Warren Ranch Rd & Hockley Meadows Dr, Hockley, TX 77447ยท$322K
W Little York Rd Pedestrian Improvements (SW30_WLY)
W Little York from Barker Cypress Rd to Queenston, Katy, TX 77449ยท$1.0M
SH 249 (CSJ: 0720-03-153, etc.)
At Spring Cypress Rd and Louetta Rd, Houston, TX 77070ยท$135K
Property Owner
๐ค
METRO
Contact: Parmjit Kang
4 projects ยท $2.9M
View company profile
1900 Main St., Houston, Texas 77002
Design Firm
๐๏ธ
Gauge Engineering.com
4 projects ยท $2.8M
View company profile
11750 Katy Freeway, Suite 400, Houston, Texas 77079