Project intelligenceTDLR TABS2024006686New Construction
Funding type

This project involves public funds, public land, or is a Federally funded roadway project.

US 60 (CSJ:0168-07-043, ETC.)

From: Divided 4-Lane To: Tierra Blanca Crk Bridge, Hereford, TX, 79045

Target date passed (Jan 2026)Review Complete

US 60 (CSJ:0168-07-043, ETC.) is a new construction project at From: Divided 4-Lane To: Tierra Blanca Crk Bridge, Hereford, in Deaf Smith County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Scheduled to finish Jan 2026 per its TDLR filing; no final inspection recorded yet. The project has an estimated value of $24.8M across about 66,510 sq ft.

Estimated project value
$24.8M
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
66,510 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$372/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
1y 8mo
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Dec 5, 2023759 days across supplied datesJan 2, 2026

4 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Review complete · TDLR filing

    The filing records completion of the accessibility review.

    Same day as the preceding date shown.

    Source: TDLR filing

    View source record
  3. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    148 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    611 days after the preceding date shown.

    Source: TDLR filing

    View source record

Review Complete

Design review complete, construction may proceed

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 79045 (Hereford)

One email per change. Unsubscribe in one click. Privacy.

US 60 (CSJ:0168-07-043, ETC.) is a New Construction project located at From: Divided 4-Lane To: Tierra Blanca Crk Bridge, Hereford, TX 79045 in Hereford, Texas. The project has an estimated value of $24.8M covering 66,510 sq ft. TxDOT District: Amarillo is the property owner and CP&Y is the design firm of record. The project was registered with TDLR on December 5, 2023.

Frequently Asked Questions

What is US 60 (CSJ:0168-07-043, ETC.)?

US 60 (CSJ:0168-07-043, ETC.) is a new construction project at From: Divided 4-Lane To: Tierra Blanca Crk Bridge in Hereford, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Rehabilitation of existing roadway to install drainage, concrete paving, sidewalks and ramps along US 60 through the town of Hereford, Texas.

Is US 60 (CSJ:0168-07-043, ETC.) open in Hereford?

US 60 (CSJ:0168-07-043, ETC.) was scheduled to finish construction in Jan 2026 according to its TDLR registration, but TDLR has not recorded a final accessibility inspection, so its opening status is not confirmed in the public record.

Where is US 60 (CSJ:0168-07-043, ETC.) located?

US 60 (CSJ:0168-07-043, ETC.) is located at From: Divided 4-Lane To: Tierra Blanca Crk Bridge, Hereford, TX, 79045, in Deaf Smith County.

Who is the owner or developer of US 60 (CSJ:0168-07-043, ETC.)?

TxDOT District: Amarillo is the property owner/developer of record for US 60 (CSJ:0168-07-043, ETC.), per its TDLR project registration.

Who is the architect or design firm for US 60 (CSJ:0168-07-043, ETC.)?

CP&Y is the design firm of record for US 60 (CSJ:0168-07-043, ETC.), according to its TDLR filing.

How much does US 60 (CSJ:0168-07-043, ETC.) cost and how big is it?

US 60 (CSJ:0168-07-043, ETC.) has an estimated construction value of $24.8M and approximately 66,510 square feet (about $372/sqft), based on its TDLR filing.

Scope of Work

Rehabilitation of existing roadway to install drainage, concrete paving, sidewalks and ramps along US 60 through the town of Hereford, Texas.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

From: Divided 4-Lane To: Tierra Blanca Crk Bridge, Hereford, TX 79045

34.88880, -102.45732

Watch all construction in 79045 (Hereford)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.

Get alerts for Deaf Smith

Daily email when new projects start nearby.

Start Alerts - $19/mo

Download project data

Get curated lists of projects with full contact info.

Browse Data Lists